NSU Pavement Improvement Closures on the Fort Lauderdale/Davie Campus Complete, June 8
On Sunday, May 10, 2020 NSU began work on improving paved lots and roadways on the Fort Lauderdale/Davie campus. The work will continue through Monday, June 8, 2020. There will be no parking or driving in these areas until they reopen.
The schedule for these improvements is as follows:
Phase 1 – Horvitz South Parking Lot: Complete
- May 10 – 15, 2020
- Lot reopens on May 18
Phase 2 – Mailman Hollywood Parking Lot: Complete
- May 12 – 21, 2020
- Lot reopens on May 25
Phase 3 – Horvitz North Parking Lot: Complete
- May 18 – 23, 2020
- Lot reopens on May 25
Phase 4 – Roadway:
- May 14 – 27, 2020
- Roads reopens on June 1
- Please see attachment for a map of the roadways being worked on. There may be flagmen during this time to help manage traffic.